The work breakdown structure of a market research project is given below:  
Activity
Immediate predecessors
Activity time in days
A
-
20
B
-
15
C
-
25
D
A
10
E
B
20
F
C
18
G
D
8
H
A, E
12
I
A, E
10
J
C
14
K
G, H
25
L
F, I
22
M
J
30
a) Draw the activity-on-arrow network diagram and find the project completion time.   

b) What would be the project completion time if the activity time of K is reduced by 5 days? Don’t draw the network diagram again while solving this part of the question. 