Project Management-2019


Question 2: Work Breakdown Structure of a project is given below:
Activity
Immediate Predecessors
Activity Time in Days
A
--
35
B
--
23
C
--
15
D
A
15
E
A
10
F
B
25
G
E, F
30
H
D
20
I
B
18
J
C
20
K
I, J
10
L
K
22

a) How much free float is available for activity D?                                                                     

b) Activity J takes 4 days more than its estimated time and the activity K also takes 3 more days than what it should have taken. What is the impact on project completion time?                          

c) Another activity M gets introduced which can be started after E is over and it is immediate predecessor to L along with K. It takes 20 days. What is the project completion time with this change?                                                                                                                                                

Answer:

Answer for (a) part is available at https://www.youtube.com/watch?v=Rcwe8zbnNhI. The correct answer is 0.